Ferrymuir roundabout – utility works

Energy Assets on behalf of Cala Homes need to carry out works to supply the new Builyeon Road Development with a power supply.

Attached is a plan of their route from Lovers Lane through Ferrymuir r/about and under the A9000. The plan shows 5 way TTLs but as works progress they should be able to reduce this slightly to 4 way TTLs.

  • Works start 22/07 for 7-10 days
  • TTLs will be manually controlled/monitored 07:00 to 19:00 7 days a week
  • The Council has requested longer working days to expedite the works and they will provide two dig teams